Key Activates of the Project:

 

  • 160MW Alstom Turbine Erection (Mechanical & Electrical).
     

  • Balance of Plant (BoP) Mechanical Erection such as, Fabrication & Erection of Stack, Equipments erection, Fabrication & Erection of pipes, Fuel gas system, Compressed air system, Raw service and portable water system, Auxiliary cooling water system, Overhead crane, etc.
     

  • Balance of Plant (BoP) Electrical Works such as, Main electrical equipment installation, 250MV ABB main transformer erection including oil filling and centrifuging, 800 mm dia isolation phase bus ducts installation including MIG welding, Auxiliary transformer, Station transformers, Start-up transformer, Emergency transformer, Lighting transformer & Black out generator installation, Instrumentation, Communication and security system installation, HT & LT switchgear panels, MCC panels, Control panels, Distribution board, UPS inverter, Battery charger, Diesel generator and all other kinds of equipment of the Plant, Cabling and termination of LV, HV, MV, Instrumentation & Control cables.
     

  • Water Treatment Plant (electrical, mechanical & Instrumentation) Erection.
     

  • Fire Fighting Systems (Fire Alarm & Protection) Installation.
     

  • Grounding Systems (Grounding & Arial) Installation.
     

  • Plant's Illumination System (Total plant lighting) Installation.
     

  • Supply of Workshop & Warehouse Equipments.
     

  • Assistance of Testing, Commissioning & Start-up.