Construction of Chuadanga 132/33KV Substation
im_reference_detail_6.png

Client: CCC Engineering, China

Key Activates of the Project:
​​

  • Mechanical & Electrical Erection of Substation.
     

  • Placing & Complete Erection of Main Transformer (132/33kv, 41MVA) and All Other Transformers.
     

  • Erection of Gentry and all other mechanical structures and equipment.
     

  • Erection of all Switchgear, VCT, HT Panel, LT Panels and all other Equipment.
     

  • Erection of Control & Communication System.
     

  • Installation & Termination of HT, LT & Control Panels.
     

  • Installation of Underground Earthing Mash & Lightning Protection System.
     

  • Assistance of Testing, Commissioning & Start-up.